Project: Boots UK LTD 2 Off 250000 litre bunded diesel tanks

CA Blackwell’s contracted Hartwell to design and fabricate and install 2 off 250000 litre bunded oil tanks for stand-by generators on their central distribution depot in Nottingham.

The tanks were built to BS 799:5 Type J and were photographed above leaving our depot to go for specialist paint coating. Whilst been a relatively simple fabrication the challenge with this contract was again down to physically shipping the tanks from A to B. At 25mx4.5mx4.5m the haulier was only allowed to travel between 12pm and 5am during selective nights.

Both tanks were delvered on schedule and were installed using a single lift 250T Demag crane on full ballast.